Why in order to get the correct phase values roll-up, when Phase value is the sum of activity values, I must click F8 after formula execution? I was expecting for the value be computed automatically whenever a value is changed no matter if manual or by a formula.
Is there a way to make Cost & Material to calculate automatically after a Scheduling run?

By the way I consider rolled-up % duration not of much value even if calculated using weights, a simple mathematical computation easy to set-up in Spider Project, but as I can see from other postings some people are hooked on these percentages. At home we follow individual activities float, volume of work, remaining duration and projected finish dates. Maybe at some point I will be asked to report on these percentages and want to make sure they roll-up as per my requirements.
Replies