Qty / Manhour

Hi All,

We got a new project and the client ask to prepare progress report and claim base on the manhours.

I think is not right cause the contract to them is lump sum re-measurement. I have proposed to them the progress report and claim base from installed qty, but they don't agree they still ask to submit manhours. any advise

Regards

R
ronron martinez 👤 Member for 16 years 6 months

Hi Mike,

If I make manhour as per the quantity I end up supplying a lot of workers.

Cause the client estimated Manhour for every quantity is over allocate?

Do you have construction activities man-hours?

Regard

Ron

M
Mike Testro 👤 Member for 20 years 6 months

Hi RonRon

You can make a direct extract of manhours from quantities using a simple percentage of Hours per Unit of measure.

It doesn't matter how accurate it is just so long as you use the same ratio for each report.

My motto is "Give then what they want" but not necessarily how they want it.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
Haque Nawaz
10 posts
EViLL1
1 posts
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts