Qty / Manhour

3 replies [Last post]
ronron martinez
User offline. Last seen 7 years 37 weeks ago. Offline
Joined: 19 Nov 2009
Posts: 41

Hi All,

We got a new project and the client ask to prepare progress report and claim base on the manhours.

I think is not right cause the contract to them is lump sum re-measurement. I have proposed to them the progress report and claim base from installed qty, but they don't agree they still ask to submit manhours. any advise

Regards

Replies

Gary Whitehead
User offline. Last seen 5 years 16 weeks ago. Offline

Why would you use the client's estimate of manhours instead of your own?

ronron martinez
User offline. Last seen 7 years 37 weeks ago. Offline
Joined: 19 Nov 2009
Posts: 41

Hi Mike,

If I make manhour as per the quantity I end up supplying a lot of workers.

Cause the client estimated Manhour for every quantity is over allocate?

Do you have construction activities man-hours?

Regard

Ron

Mike Testro
User offline. Last seen 27 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi RonRon

You can make a direct extract of manhours from quantities using a simple percentage of Hours per Unit of measure.

It doesn't matter how accurate it is just so long as you use the same ratio for each report.

My motto is "Give then what they want" but not necessarily how they want it.

Best regards

Mike Testro