How to assign weights to Schedule ?

1 reply [Last post]
Irfan Khan
User offline. Last seen 9 weeks 21 hours ago. Offline
Joined: 19 Jul 2009
Posts: 138

I am exploring the way that how to assign weights to my schedule

I am using cost & resource loaded schedule

Duration Type = Fixed Duration & Units

% complete type = Duration

Duration % complete = 12.33%

Schedule % Complete = 20.35%

Performance % Complete = 17.89%

Here I want to know the way of assigning the weights to each activity coz my manager is asking to show me the planned weights & Actual Weights.

Thax in advance…… J

Replies

Jose Frade
User offline. Last seen 3 years 19 weeks ago. Offline
Joined: 7 Jun 2005
Posts: 144
Groups: None

Not sure if I got your point because if the Schedule is populated with cost and resources then the weights are already there.

Planned weights can be taken from Base line while Actual weights can be taken from progress made on each period (calendar / finacial / etc)

 

BR

 

JMFrade