Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Assign Weights to Entire Activity & WBS Summary Level

1 reply [Last post]
Irfan Khan
User offline. Last seen 28 weeks 1 day ago. Offline
Joined: 19 Jul 2009
Posts: 138

hi to all,

Here i am wondering a way to assign weights to my entire activities as well as WBS level.

My schedule is loaded with Man-hours but now my Client asking to show the weight on the schedule.

I have checked in P6 & there is no any default column i found where i am able to show the weights, but i guess by the help of UDF we can show those weightages.

any reply in regard will be highly appreciated.

 

Thanks in advance .... :)

Replies

Dieter Wambach
User offline. Last seen 7 years 31 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350

Hi Irfan

 

I'm not sure if I understood right.

Weight in P6 is given by budgeted units (labour or non-labour), material units or costs (labour, non-labour, material, expenses) or the sum.

In the Activity Usage Profile you can easily create the s-curves. A better formatting would be in Excel or any other spreadsheet: Create a report in csv format --> read into Excel --> format the graphics --> print.

If you'll need an explicite weight independent from budget (but why?) you can use a UDF.

If you'll mark "Show Grand Totals" in Group&Sort iP6 will sum up. 

Good luck with your planning

Dieter