how to do weights in activities

3 replies [Last post]
walid Lahiani
User offline. Last seen 8 years 2 weeks ago. Offline
Joined: 6 Nov 2010
Posts: 45
Groups: None

 

Good morning,

If I have a scope of work of one project ,

-I extract activities,durations,relationships,I do the WBS,OBS

-Now ,how to do weights

Replies

Imran Arshad
User offline. Last seen 5 years 49 weeks ago. Offline
Joined: 6 Nov 2007
Posts: 46

Dear, You can give weighs in User defined fields.

ravirg gehlot
User offline. Last seen 7 years 31 weeks ago. Offline
Joined: 22 Sep 2011
Posts: 29
Groups: None

In P6.1 Version in WBS ...Columns ...Weightage ..Option was there where you can give weightage to WBS ...But This option is not available in P6 R8.1

 

Raymund de Laza
User offline. Last seen 8 weeks 2 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Walid,

What you will weigh in?