Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Level Of Effort progress updated

1 reply [Last post]
Izam Zakaria
User offline. Last seen 7 years 41 weeks ago. Offline
Joined: 28 May 2006
Posts: 221

Hi All,

Just wonder how normally you update your level of effort schedule activities (when you are running live schedule)? Do you change it to task dependent by the time the baseline been finalized?

Replies

SM PUM
User offline. Last seen 10 years 30 weeks ago. Offline
Joined: 15 Nov 2011
Posts: 77
Groups: None

Hi;

Level Of effort is dependant of the predecssor's and successor's completion.It will Complete with the completion of its successor.

 