Updating Level-of-Effort Activities
Forum Sponsor
Top Posters
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts
And youre in Forensic Claims? hmmmmmm......
Anyway, the LOE Activities act as a Hammock to the group it is spread across, and if you have assigned the LOE correctly (SS,FF) then your % complete will increase in relation to the Activities. You have to manually update your cost of work done allocated to these though.
Walshy
set percent complete type to physical and change it