Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Updating Level-of-Effort Activities

2 replies [Last post]
Ashish Abraham
User offline. Last seen 6 years 46 weeks ago. Offline
Joined: 28 Nov 2006
Posts: 16
Groups: None
Hello,

I am currently working on a P6 schedule with several cost loaded level-of-effort activities. Is it possible to update such activities...I mean, can I change the percent complete on these activities?

Please advise.

Thanks!

Replies

Neal Walsh
User offline. Last seen 4 years 6 weeks ago. Offline
Joined: 16 Sep 2007
Posts: 49
And you’re in Forensic Claims? hmmmmmm......

Anyway, the LOE Activities act as a Hammock to the group it is spread across, and if you have assigned the LOE correctly (SS,FF) then your % complete will increase in relation to the Activities. You have to manually update your cost of work done allocated to these though.

Walshy
Anoon Iimos
User offline. Last seen 2 years 45 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
set percent complete type to physical and change it