Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

logic for level of effort

1 reply [Last post]
daniel ishmael
User offline. Last seen 17 years 19 weeks ago. Offline
Joined: 18 Dec 2006
Posts: 3
Groups: None
Could someone explain how to link level three activities using the level 2 as level of effort..I have an idea but I just want to confirm.

Replies

Santosh Bhat
User offline. Last seen 17 weeks 1 day ago. Offline
Joined: 15 Apr 2005
Posts: 381
Note that a LOE activity is like, but not the same as a Hammock.If you want it to behave like a hammock, ensure that you only have one predecessor and one successor, else it’ll pickup the latest ES date and the earliest EF date.

-------------------
The P5 manual says:

1. A Hammock activity expands to “umbrella” the activities encompassed within it. A LOE activity acts like a “filler” activity – it compresses to fit between activities.

2. Hammocks are not scheduled using their own calendar. A LOE activity uses its assigned calendar during scheduling.

3. A Hammock activity’s duration is calculated as the earliest early start of its predecessors to the latest early finish of its successor activities. A LOE activity’s duration is calculated from the latest early start of its predecessors to the earliest late finish of its successors.