Dear all,
please help me with the questions below, thank you.
1. When i status my schedule, i notice that sometimes when i check the status of an newly started work as "start", the duration in "at completion" row will change to a duration longer than the original duration. so i have to change it back to original duration, either by input a figure in "remaining duration" and in this case i have to do a math first (original minus actual). sometimes i just change the figure in "at completion" to make it equal to the one in "original". any suggestion why?
2. what is more frustrating is that, some times the figure in "at completion" does not change at all when i status an activity, but after i press F9 and schedule it. the figure changes, which means everytime i have to status and schedule first, and check the duration and manually change it, and then scheudle it again. any suggestion?
BR
Forrest
Replies