question about labour units in P6

1 reply [Last post]
Yaser A. Al-Bustanji
User offline. Last seen 1 year 42 weeks ago. Offline
Joined: 12 May 2010
Posts: 27
Groups: None

Hi all,
I have found a problem in my primavera program. I didnt assign any labour type resources to the activities of my program. But in Budget Labour units column, Primavera is showing some values? 
Why it is coming like this?

Thanks in advance.......

Replies

Raymund de Laza
User offline. Last seen 3 days 16 hours ago. Offline
Joined: 22 Nov 2009
Posts: 762

Hi,

You might  have copied your program from other programs that have labors assigned in the activities.

Yo need to reset labor units of all activities to zero.

 