Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Budget at Completion vs Budgeted Expense Cost

1 reply [Last post]
Farzin Farsi
User offline. Last seen 3 years 41 weeks ago. Offline
Joined: 3 Nov 2008
Posts: 20

Hi there,

 

In one of my many projects,  I have a Budgeted Expense Cost for a selected activity (let’s say $500K)  but  Budgeted At Completion column is still zero.

I have more than 15 projects with almost the same structure with expense cost which do not have this issue (Budgeted At Completion is not zero).

Any one knows a solution for this?

I have checked all project properties and all are the same.

Regards

Farzin

Replies

Daniel Limson
User offline. Last seen 5 years 4 weeks ago. Offline
Joined: 13 Oct 2001
Posts: 318
Groups: None

Hi Farzin,

The terminology "Budgeted at Completion" may be a little ambiguious but they maybe  actually referring to "forecast Cost at Completion". You need to learned about the EVM - Earned Value Management and/or EVA process. To calculate your forecast cost at completion  = (Budgeted - Earned to-date) / Actual to-date

Regards,

Daniel