Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Require Activity % Complete equal to Expense % Complete

4 replies [Last post]
Irfan Khan
User offline. Last seen 31 weeks 6 days ago. Offline
Joined: 19 Jul 2009
Posts: 138

Hi to all experts,

 

I am using Primavera P6 R8.2

 

Here i am working with the schedule with 4,000 activities & almost 2,200 activities i have loaded Cost though Expenses.

The Problem i am facing that for example : one activity having 50% of  Activity % Completed so far, but when i am looking @ the Expenses Tab & its not showing me any actual cost for the same activity. Even i have tried to Import & Export throuhg excel in order to reflect the Activity% complete into Expenses % compete but due to (*) sign the values in exel sheet cant be modified.

 

Please anyone can help me in this regard.........i will be highly obliged  

 

Replies

Irfan Khan
User offline. Last seen 31 weeks 6 days ago. Offline
Joined: 19 Jul 2009
Posts: 138

Thank you Mr. Zoltan.......... i got what i was looking for.

Zoltan Palffy
User offline. Last seen 7 weeks 5 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

no the global change suggestion will not work you can not cross % complete between activites and expenses even is you create a UDF

I have supplied the solution here

http://pmsite.com/forums/viewthread/3203

 

Irfan Khan
User offline. Last seen 31 weeks 6 days ago. Offline
Joined: 19 Jul 2009
Posts: 138

i tried to resolve it through Global Change......but unfortunately i didnt get way to fix it.... :(

Ahmed KHR
User offline. Last seen 6 years 46 weeks ago. Offline
Joined: 10 Nov 2010
Posts: 65

Hi Irfan,

 

Try to use global change (Expense % = Activity %)

 

Regards