will someone please explain how can get the planned%complete in p6?
how can get the planned%complete
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
thanks so much Shareef. It was helpful.
Hi Shima
In P6 the 'Schedule % Complete' gives the Planned % Complete.---You have to save a copy of the programme as Baseline to get the correct schedule % complete.
Now at the activity level this % is based on durations. If you use the help hint the formula for calculation is clear...But at summary level the percentages are based on costs.
ie.. Planned Value Cost / Budget at Completion,,,, where Planned Value cost for each activity= Shedule % * Budget for the activity.
As such the Schedule% (Planned % ) can be compared to performance % complete and not to Duration % complete ---at summary levels.
The other way around is to create a copy of the programme and auto update actuals and take the Duration complete. This Duration % complete can be used as a Planned % to compare with Actual % if you have not loaded cost as such could not get performance % complete.
Now to combine both in the same layout is not possible as BL Duration % complete dont rollup at summary levels.
Hope this helps.
Regards
Shareef