Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to Get Project Percent Complete

4 replies [Last post]
Ahmad Obeidat
User offline. Last seen 5 years 1 week ago. Offline
Joined: 26 Mar 2019
Posts: 15
Groups: None

Good day,

I have just made a new revised program for the project 

I have added new activities and loaded the material resources for the remaining activities (Concrete).

How I can calculate the project percent complete?? depending on what?

how P6 is calculating the schedule % complete and units % complete? 

when i roll up for all the project it gives a schedule % complete ?? is this accurate or what?

 

Regards,

 

Replies

Zoltan Palffy
User offline. Last seen 2 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

Rafael has it correct you can only use duraton % complete and roll that up. In the gGroup and sort select show gand totals

Rafael Davila
User offline. Last seen 20 weeks 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

If the schedule is not resource or cost loaded then your only option might be to use Duration % Complete, an option I consider foolish at the project level.

If cost and resource loaded you can use Cost/Resources/Materials/Effort to calculate % complete but usual practice is to generate Progress-S Curves as they provide more information.  You can convert values to % of total at some cost as with values [current and total] you can estimate both but with % only you cannot figure out the values.  Better show both, if to show only one of the two then use values and nothing is lost. 

With the exception of duration at the project level all the options provide relevant progress information.  

Progress-S-Curves

Download Image Link

Ahmad Obeidat
User offline. Last seen 5 years 1 week ago. Offline
Joined: 26 Mar 2019
Posts: 15
Groups: None

Hi Zoltan,

the program is not uploaded with the resources, so I don't know what measures I should consider calculating the project percent complete!

my question is there is any way to get that from primavera as the schedule percent complete??

Zoltan Palffy
User offline. Last seen 2 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

this depends on what your measuing stick is