How Can I get list of due/Overdue activities in P6??

1 reply [Last post]
Nitin Chauhan
User offline. Last seen 10 years 13 weeks ago. Offline
Joined: 12 Mar 2014
Posts: 6
Groups: None

HI,

Can any please help how can I generate layout that displays activities which has either been due or overdue.

 

Regards

 

NC

Replies

Gary Whitehead
User offline. Last seen 5 years 11 weeks ago. Offline

Filter for baseline finish less than or equals data date