P5 - Issue with 2 default calendars

2 replies [Last post]
Richard Evans
User offline. Last seen 12 years 37 weeks ago. Offline
Joined: 8 Aug 2005
Posts: 3

The issue is 2 default calendars are ticked. If I try to untick one the message we get is {One default value is required.} If we try to assign another calendar as default the event code 2DVWV-3590-8 occurs. has any one experienced this? 

Replies

marco mavil
User offline. Last seen 12 years 14 weeks ago. Offline
Joined: 11 May 2012
Posts: 2
Groups: None

The problem is in the database not in primavera.

Did you fixed it? Upgrading doesnt work :S

Ronald Winter
User offline. Last seen 3 years 22 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None

Richard,

 

You are trying to troubleshoot a problem on a really outdated piece of software.  P5 is so old that I believe that Oracle/Primavera no longer supports it.  Version 8 is the current version.  I suggest that you ‘solve’ this problem by upgrading your software.  There are literally hundreds of fixes and many good added features in the new software.  Good luck!