Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Why does Cost is not updated when progress % is updated...Headache of P6

7 replies [Last post]
Haresh Jayanth
User offline. Last seen 6 years 44 weeks ago. Offline
Joined: 24 Aug 2006
Posts: 219

Dear All,

If we are not using Pice/unit in P6 and directly entering cost in P6 , the cost is not getting update in P6, if we are updating the activity in P6........Why this is happing.....Pls let me know......

 

regards,

 

Haresh Jayanth - PMP , PSP

Replies

Zoltan Palffy
User offline. Last seen 7 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

glad I could help 

Ruel Camaquin
User offline. Last seen 7 years 20 weeks ago. Offline
Joined: 1 Sep 2008
Posts: 6
Groups: None

Thanks Master Zolthan...

Zoltan Palffy
User offline. Last seen 7 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

go to projects directory make sure that your project is highlighted check your clacluations settings under resource assignments it should be subtract actual from at completion. 

also the recalculey actual units and costs when duration % complete changes 

and link actual and actual this period units and cost

In the defaults tab the duration type should be Fixed durations and units/time

then run a global change where duration % complete = physcial % complete

the price/unit has to be 1 at least 1 becasue anything multiplied or divided by 0 = 0 

Ruel Camaquin
User offline. Last seen 7 years 20 weeks ago. Offline
Joined: 1 Sep 2008
Posts: 6
Groups: None

Hi Zoltan,

It's been a while from the last time we exchange our plesanatries...

With regards to the query above from Haresh, just like to know why is the budgeted cost we directly put on P6 turns to zero (0) when we input the actual dates and/or physical % complete? Hoping to hear from the Master the soonest!

Ruel

Ruel Camaquin
User offline. Last seen 7 years 20 weeks ago. Offline
Joined: 1 Sep 2008
Posts: 6
Groups: None

Hi Zoltan,

It's been a while from the last time we exchange our plesanatries...

With regards to the query above from Haresh, just like to know why is the budgeted cost we directly put on P6 turns to zero (0) when we input the actual dates and/or physical % complete? Hoping to hear from the Master the soonest!

Ruel

Ruel Camaquin
User offline. Last seen 7 years 20 weeks ago. Offline
Joined: 1 Sep 2008
Posts: 6
Groups: None

Hi Zoltan,

It's been a while from the last time we exchange our plesanatries...

With regards to the query above from Haresh, just like to know why is the budgeted cost we directly put on P6 turns to zero (0) when we input the actual dates and/or physical % complete? Hoping to hear from the Master the soonest!

Ruel

Zoltan Palffy
User offline. Last seen 7 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

go to projects directory highlight your project go to calculations tab under resource assignments select 

recalculate actual cost and units whne duration % complete changes 

and make sure to update duration % compelte