Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Calender and original durations

4 replies [Last post]
Anthony Peters
User offline. Last seen 6 years 44 weeks ago. Offline
Joined: 5 Apr 2007
Posts: 18
Groups: None

Hey,

Ive just set up a new project. For that project i have set up a calender where the working hours are 11hrs a day, 7 days a week. I have made this calender the activity and project default calender. I have also gone into user preferences and changed the work time to 11hrs per day.

However when i add a new activity, it automatically comes up with an 8hr duration as opposed to an 11hr duration. Also the times that are shown are 00.00 - 14.30 which isnt even 8 hours!! It should show 06:30 - 17:30 as per the calender. Obviously somethings going wrong, can anyone shed any light?

Replies

Mike Testro
User offline. Last seen 1 day 15 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Anthony

Do you have any resource allocations with different calendars?

Best regards

Mike Testro

Baris Hazar
User offline. Last seen 7 years 39 weeks ago. Offline
Joined: 4 Dec 2009
Posts: 39

Make sure that you have completed step 2 as i indicated. Because 'default duration' is another setting and different than 'hours/day'.

b

Anthony Peters
User offline. Last seen 6 years 44 weeks ago. Offline
Joined: 5 Apr 2007
Posts: 18
Groups: None

Hi,

Ive done all of the above but the new activities still come up with 8 days! Any other suggestions welcome!

Baris Hazar
User offline. Last seen 7 years 39 weeks ago. Offline
Joined: 4 Dec 2009
Posts: 39

Hi,

 

After arranging calendar settings;

1- Go to Edit-->User Preferences-->Time Units--> Duration Format="Hours"

2- Go to Admin-->Admin Preferences-->General-->Activity Duration-->Default Duration=11h

3-Go to Admin-->Admin Preferences-->Time Periods Check the check box for "Allow users to specify the number of work hours..."

4- Go to Edit-->User preferences-->Time Units-->Hours per Time Period; Set Hours/day=11 h

Without step 2, you add 8h/day when you add a new activity by default.

 

Hope this helps

 

baris