Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Issue with Original Duration in P6 when importing MS Project xlm file

1 reply [Last post]
katrin enders
User offline. Last seen 8 years 2 weeks ago. Offline
Joined: 2 Aug 2008
Posts: 19

Hi All,

I have a schedule prepared in MSP and I import it to P6 as an xml file. Durations of the tasks in the imported file appears in Original Duration

column (as expected). However, when I change the duration of a task in the Original Duration in P6, the bar in the Gannt Chart does not get longer

or shorter. It gets longer or shorter when I change the duration in the Remaining Duration column.

In fact the Original Duration and Remaining Duration update in Ms Project but after saving the MS File Project as XLM to import to Primavera P6 this

no longer works.

Its as if the calculation in P6 is disabled for this imported Project and I do not know where.

Because If i start a new project in P6 all works as usual and Original Duartion and Remaining Duartion up date automatically

Any ideas whats wrong?

thanks Katrin

 

Replies

Arend Woltjer
User offline. Last seen 8 years 44 weeks ago. Offline
Joined: 26 Sep 2011
Posts: 74
Groups: None

BY UTKUL CIL: I found the answer in one of the previous posts in forum. "Link Budget and At Completion for not started activities" checkbox under "Projects window => Calculations Tab" need to be checked. the problem is solved then.

 

To Katrin: there are many posts on this forum that could have anserwed your question.

I use to tell people: RTFM..

 

Regards,

Arend