Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

When I make down the original duration , the ressource allocation became overloaded but the unit/TIME didn't change

6 replies [Last post]
walid Lahiani
User offline. Last seen 8 years 17 weeks ago. Offline
Joined: 6 Nov 2010
Posts: 45
Groups: None

Hello ,

Explication :

Imagine we have a Labour who works 8h/day and an excavation task ,

the original duration of the task is 10 days

so ,this laber will work a total of 80h ,

If i change the original duration to 2 days ,normally this laber have to work  40h/day => 5 labers/ day

But in the table we have always 8h/day (unit/time) =>one laber only

Thank you

 

 

Replies

BONG YAGAHON
User offline. Last seen 1 year 6 weeks ago. Offline
Joined: 5 Oct 2009
Posts: 43

 

Hi,

What is meant by  "Explication"    as you telling in first line?

ty.

BONG YAGAHON
User offline. Last seen 1 year 6 weeks ago. Offline
Joined: 5 Oct 2009
Posts: 43

 

Hi,

What is meant by  "Explication"    as you telling in first line?

ty.

pei tang
User offline. Last seen 12 years 7 weeks ago. Offline
Joined: 12 Oct 2012
Posts: 2
Groups: None

i want to say "fixed duration and units" and "fixed units" should produce the same results.

Amit Parmar (PMP)
User offline. Last seen 12 years 10 weeks ago. Offline
Joined: 12 Nov 2010
Posts: 94
Groups: None

Glad to be of help :)

walid Lahiani
User offline. Last seen 8 years 17 weeks ago. Offline
Joined: 6 Nov 2010
Posts: 45
Groups: None

Good morning

Thank you for this very interesting table

Amit Parmar (PMP)
User offline. Last seen 12 years 10 weeks ago. Offline
Joined: 12 Nov 2010
Posts: 94
Groups: None

Hi,

Change "Duration Type" to "Fixed Units" in the activity and you would be able to see the changed rate. By default your "Duration Type" would be " Fixed Duration & Units".

 

Duration Type follows following formula :

  • Remaining Duration = Remaining Units / Remaining Units/Time
  • (Original/Planned) Duration = (Budgeted/Planned) Units / (Budgeted/Planned) Units/Time

hence changing the Duration Type affect the resource and duration calculations in the following ways :

 

    Duration Type
Change UnitsChange Duration
    Change Units/Time
    Add 1st resource
    Add additional resources
    Fixed Units/Time
DurationUnits
    Duration
    Units
    Duration
    Fixed Duration & Units/Time
Units/TimeUnits
    Units
    Units
    Units
    Fixed Units
DurationUnits/Time
    Duration
    Units
    Duration
    Fixed Duration & Units
Unit s/TimeUnits/Time
    Units
    Units
    Units/Time of each Resource