Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Resourse profile Graph

6 replies [Last post]
Arun Vasanth
User offline. Last seen 5 years 42 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 200
Groups: GPC Qatar

Dear Sir 

Attached is a graph generated after loading the resource.I want to show the planned and cumulative(left and right )  in Nos instead of d.Is there any way to show the numbers on top each monthly  bars as same like  generating in the excel....  Awaiting your reply

702
untitled.jpg

Replies

kumar s
User offline. Last seen 9 years 5 days ago. Offline
Joined: 26 Jan 2010
Posts: 159

ARUN,

if your working hours per day is 10hrs then you divide it by 10 only....

calendar wil not matter.

 

cheers

Arun Vasanth
User offline. Last seen 5 years 42 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 200
Groups: GPC Qatar

Thank you Kumar 

Friend help me for this one also 

Please define me about this average .....

My program is a 6 day calendor with 10 hrs working time .How much I have to put as Average ?????

kumar s
User offline. Last seen 9 years 5 days ago. Offline
Joined: 26 Jan 2010
Posts: 159

Dear Arun,

here is the option.

go to the reosurce usage profile then right click in the graph.there you will find the options for DATA and GRAPH.

then in the graph there is a option for calculate  average click it,here you have to divide the intervals by either 12hrs(shift wise) or 24hrs(day wise) based on the usage of your resources.you can mention N in the unit of measure.

 

Regarding Numbering each bar is not possible and still have to wait.you can use the excel sheet for better presentation. 

 

cheers

Arun Vasanth
User offline. Last seen 5 years 42 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 200
Groups: GPC Qatar

Any way to change the d units I want the manpower in numbers ....

How to export the units to excel

D Artagnan
User offline. Last seen 2 years 42 weeks ago. Offline
Joined: 19 Sep 2008
Posts: 207

none that i know...

the thing is, the curve that P6 can produce is pretty limited and if you want to have more flexibilities, you have to use external tools such as excel, access, etc.

i would also be glad to know if what you are asking is possible.

jingjun zou
User offline. Last seen 4 years 24 weeks ago. Offline
Joined: 8 Apr 2008
Posts: 6

I think it is impossible, Primavera only provided two options: day and cost.

Normally I use Excel to make the S curve more flexiable. Input and maintain resources in Primavera is a difficult work, especially in a  complicated project with very many activites.