Hii,
I am using P6.7 version. Currently i am planning for Integrated cement plant project. The issue which i am facing now is...
I have created the 18.5 month Schedule with assigning of resouses. I am one query regarding is that. Suppose I have created One activity of say duration 20 days. Now with respect to this activitity i have assigned 4-5 resouses say (Excavator, dumper, helper and supervisor etc).
Now the point is i want to distribute Supervisor and helper for the whole duration of activity (i.e. 20 days). and at the same time Excavator i want to use for starting 15 days (not being used for last 5 days) and Dumper i want to use for last 10 days (not being used for starting 10 days).
So, can you help me out in this accout that how i would assign the resourses for one activitiy (20 days) with above distribution of resorses by given day wise.
Please tell the process..
Rgds,
Pankaj