Resource Usage Profile

2 replies [Last post]
Rohit K
User offline. Last seen 4 years 44 weeks ago. Offline
Joined: 2 May 2008
Posts: 73

Guys,

I have developed a schedule in P 6.0, with resource loading. Following is the problem I am facing when viewing the Resource Usage Profile. The calender for both activities and resource selected is common 7 x 24 hrs.

I have say a resource mason with Defaults Units / Time : 8/d

Max Units / Time: 200/d ( ie 200 / 8 = 50 nos for the project duration)

Have assigned this to an activity PCC from 01.06.11 to 26.06.11 (25 days duration)

Now I want to allocate 8 masons for 25 days so have entered in Remaining Units / time : 64/d ( 8 * 8 ie 8 masons * 8 hrs / day for the entire 25 day durations)

But when I view in the Resource Usage Profile, I am able to view mason being allocated to only at the start of the activity and not being spreading all along the 25 day durations.

Rohit

686
pm.jpg

Replies

Rohit K
User offline. Last seen 4 years 44 weeks ago. Offline
Joined: 2 May 2008
Posts: 73

Guys,

Thank you all for the help.

692
prim71431-001.jpg
Solved it. Here is the solution to it, select the period as per requirement but experts say to go for hours.

Rohit

thaer ghanim
User offline. Last seen 13 years 34 weeks ago. Offline
Joined: 13 Sep 2011
Posts: 19
Groups: None

HI  

 

change the time scale to Days/week