Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to group and sort for a single resource ID into multiple criteria in resources usage profile

1 reply [Last post]
Galav Dani
User offline. Last seen 7 years 8 weeks ago. Offline
Joined: 6 Aug 2014
Posts: 4
Groups: None

Hello experts...

Imagine there is a resource defined as “Fitter” and I had allocated that resource in many activities in schedule. 

Now my schedule comprises of different units called as unit A, B, C Etc… 

Now during resource usage profile how can I show unit wise amount of over allocation of “Fitter” ?

What method should i use?

Replies

Raymund de Laza
User offline. Last seen 18 weeks 4 days ago. Offline
Joined: 23 Nov 2009
Posts: 762
Hi...Set a Max Unit / time for the Resource.