I do not use P6 nor have it but believe horizontal/timescale you can adjust while the vertical is adjusted by the software using your histogram height and maximum versus minimum values.
If this is so probably the maximum values do happen at a different time not being shown.
Suggest trying to set the histogram to display only the selected values (manpower) for selected activities, for those occurring only at the time span of interest.
Unfortunatley, this does not answer my question. I am looking to cap the total scale at 30 but it is showing up to 63+ due to a previous weeks high budgeted manhours .
Thank you for the help.
Member for
15 years
Member for15 years
Submitted by Walid Lahiani on Wed, 2012-01-25 11:09
Member for
15 yearsGood morning,may be this is
Good morning,
may be this is the response :
In activity usage profile
Show usage for selected activities (not for all activities)
Member for
13 years 9 monthsThat also didnt work. What I
That also didnt work. What I am really trying to do is manualy alter the y axis numeric values. I want the graph to top out at 30 instead of 68.
Is this even possible?
Member for
21 years 8 monthsI do not use P6 nor have it
I do not use P6 nor have it but believe horizontal/timescale you can adjust while the vertical is adjusted by the software using your histogram height and maximum versus minimum values.
If this is so probably the maximum values do happen at a different time not being shown.
Suggest trying to set the histogram to display only the selected values (manpower) for selected activities, for those occurring only at the time span of interest.
Best regards,
Rafael
Member for
13 years 9 monthsUnfortunatley, this does not
Unfortunatley, this does not answer my question. I am looking to cap the total scale at 30 but it is showing up to 63+ due to a previous weeks high budgeted manhours .
Thank you for the help.
Member for
15 yearsIf it's not the solution ,and
If it's not the solution ,and you have the solution , send me it
thank you
Member for
15 yearsGood morning,I hope I
Good morning,
I hope I understand your question :
you go in the top of the graph ,"in display..." ,you right click and then choice options ,then in data change the scale by "unit"