Hi all
I'm a recent graduate who's just got his first role in planning. This site looks to be a good way to chat to other planners.
I've been on a basic Primavera course but I'll be doing plenty of updating programmes etc and have encountered my first problem using P6.
If anyone could help I'd be most grateful....
I've inherited a programme where there is are two activities that start on a monday and need to end the following Friday. The odd thing is that when I change the start and end dates to suit - one activity says the duration is 5 days, and the other 4 days.
They both need to last the same duration with matching start/end dates - is there something wrong in the ways the activities are 'set up'? It just looks odd that when 2 identical tasks need to last a week, one says 5 days duration and the other doesn't match.
Replies