Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

User defined field / activity code with several data for one activity

1 reply [Last post]
nj iop
User offline. Last seen 11 years 13 weeks ago. Offline
Joined: 2 Apr 2014
Posts: 2
Groups: None

Hi,

I would like to know if it is possible to create an activity code or user defined field with several data for one activity (like for the predecessors where the activity can have sereval of them).

Best Regards,

Replies

Rangarajan Ramaswamy
User offline. Last seen 2 years 40 weeks ago. Offline
Joined: 1 Dec 2009
Posts: 24

Yes its possible. Add all the activity codes that you want to one activity and then enable the activity codes column and then just use fill down to copy the activity codes to all the required activities.