Same value of Budget Labor Units and Custom Defined Field using global change in P6

6 replies [Last post]
Num Lock
User offline. Last seen 11 years 37 weeks ago. Offline
Joined: 15 Oct 2006
Posts: 27

Dear All,

Hi, I already have values in my custom defined field "WF". I cannot use global change so my Budget Labor Units will be equal to the values in my custom defined field "WF". Any work around? 

Thank you.

Regards,

Num

Replies

Num Lock
User offline. Last seen 11 years 37 weeks ago. Offline
Joined: 15 Oct 2006
Posts: 27

Hi, anyone has solution for this one? Thanks.

Num Lock
User offline. Last seen 11 years 37 weeks ago. Offline
Joined: 15 Oct 2006
Posts: 27

Hi, anyone has solution for this one? Thanks.

Num Lock
User offline. Last seen 11 years 37 weeks ago. Offline
Joined: 15 Oct 2006
Posts: 27

Hi, I simply use 2 global change:

1. Global change 1 (Activities):

user_number6 = _sc wf

2. Global change 2 (Activity Resource Assignment):

Budgeted labor units = user_number6

Num Lock
User offline. Last seen 11 years 37 weeks ago. Offline
Joined: 15 Oct 2006
Posts: 27

Hi I already changed the security profiles but still it doesn't work.

Amit Parmar (PMP)
User offline. Last seen 12 years 9 weeks ago. Offline
Joined: 12 Nov 2010
Posts: 94
Groups: None

Hi,

Can you please tell me what formula are you using while using global change.

Regards

Amit Parmar

Check out my blog on PrimaveraBlog at http://www.primaverablog.in

Raymund de Laza
User offline. Last seen 3 weeks 5 days ago. Offline
Joined: 22 Nov 2009
Posts: 762

Hi Num Lock,

Please check your Security Profile assigned to you if you are not a superuser. You might not allowed to edit part or whole of the project data.

 

Hope this will help.

 

Regards,

 

Raymund