Progress Line in Bar Chart

1 reply [Last post]
Shah. HB
User offline. Last seen 31 weeks 1 day ago. Offline
Joined: 25 Nov 2008
Posts: 773

Hi to all

 

Is there any option in P6 and its higher version to display progress line on bar chart ?

 

Regards

Shahul

Replies

Andy Power
User offline. Last seen 3 years 43 weeks ago. Offline
Joined: 30 Aug 2006
Posts: 43
Groups: None

Hi Shahul

Right click on your Gantt chart and select bars, you should then be able to turn on the actual work/progress bar.

Andy