Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Max units per time not matching "Limit" line in recourse usage profile bar chart

No replies
Huss PS
User offline. Last seen 1 year 37 weeks ago. Offline
Joined: 2 Aug 2022
Posts: 7
Groups: None

Hi All,

 

I am using P6 V21.

"Limit" line in "Reosrce usage profile" window it is showing above 50h/d (Max units/time set when adding resource).

Has anyone experience similar issue? What could be the reason? and how to fix it?

 

PS: I tried to upload snapshot but unable to see images or load images on this website. probably becasue it's not https. If i can get help on this as well, that would be great.

Thanks 

Huss PS
User offline. Last seen 1 year 37 weeks ago. Offline
Joined: 2 Aug 2022
Posts: 7
Groups: None

It Worked!!! 

You were correct. 

I deleted both calenders and added again. 

Thanks alot.

Huss PS
User offline. Last seen 1 year 37 weeks ago. Offline
Joined: 2 Aug 2022
Posts: 7
Groups: None

I checked that again. Calender for both activities and resources are same.

see below snapshot.

8277
2.png

david kelly
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 12 Feb 2016
Posts: 39
Groups: None

So, you think the llimit should be 50, but it is really 63?

 

Sounds like a Resource Calendar issue

Huss PS
User offline. Last seen 1 year 37 weeks ago. Offline
Joined: 2 Aug 2022
Posts: 7
Groups: None

It's showing 63.

Huss PS
User offline. Last seen 1 year 37 weeks ago. Offline
Joined: 2 Aug 2022
Posts: 7
Groups: None

It's showing 63.

david kelly
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 12 Feb 2016
Posts: 39
Groups: None

Can you double-click on one of the histogram bars, and report back the figures?