Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Showing Non Work Period in Bar Chart in P3e

3 replies [Last post]
Nitin Naik
User offline. Last seen 8 years 20 weeks ago. Offline
Joined: 1 Feb 2005
Posts: 27
Groups: None
Folks,

Does anyone know how to show a non working period in bar chart in P3e Version 5.0

Currently it can be shown using ’curtain’ function but it needs to done manually for each non work period.

Look forward to your replies

Cheers

Nitin

Replies

Andrew Pearce
User offline. Last seen 1 year 45 weeks ago. Offline
Joined: 11 Jun 2001
Posts: 175
If you want grahical enhancements like that then you need to buy Powerproject by Asta Developments.

http://www.astadev.com/index.asp

Not got the high power number crunching ability of Primavera but far better graphical output for use in general Construction projects
Nitin Naik
User offline. Last seen 8 years 20 weeks ago. Offline
Joined: 1 Feb 2005
Posts: 27
Groups: None
Hi,

Thanks Arthur for your reply.

I was mainly after showing a non work period throughtout barchart like you would achieve by using ’curtain’ function.

Thanks once again
Arthur Godbeer
User offline. Last seen 15 years 19 weeks ago. Offline
Joined: 24 Jul 2006
Posts: 127
Groups: None
View/Bars/Bar Settings/Bar Necking Settings.