Remove performace % by Global change

3 replies [Last post]
James bid
User offline. Last seen 9 years 48 weeks ago. Offline
Joined: 8 Oct 2009
Posts: 50

Dear experts!

 

May I ask your help on what parameter to use in removing the performance % in each activity.

I tried the

If

Activity status is not equal to Not started

Then

Physical % = 0

 

But the % didnot change.

 

Hoping to share your knowledge on this matter.

 

Many Thanks

Chris

Replies

Evans Musyoka Mat...
User offline. Last seen 8 years 40 weeks ago. Offline
Joined: 16 Feb 2009
Posts: 5
Groups: None

Simply deprogress by,

 

If

Physical % Complete is within range of 1% and 100%

 

Then

 

Physical % Complete = 0%

Duration % Complete = 0%

Actual Start =            

Actual Finish =

James bid
User offline. Last seen 9 years 48 weeks ago. Offline
Joined: 8 Oct 2009
Posts: 50

Thank you Roger for the detailed information you had given to me.  My programme was reset already.

Roger Booth
User offline. Last seen 4 years 34 weeks ago. Offline
Joined: 26 Oct 2006
Posts: 74
Groups: None

1. Choose 'Enterprise', 'Projects' and select the calculations tab. Choose 'Link budget and at completion for not started activities' and 'Reset remaining duration and units to original'

2. Choose view,columns and add the columns for 'Actual labor units' and 'Actual non labor units'

3. Choose tools, schedule and set the data date equal to the project start date and schedule. To find the project start date, choose Enterprise, Projects. click on the dates tab and note the planned start date.

4. For the first activity in the list, set the actual labor units to zero. Highlight the activities in this column and choose edit, fill down

5. Do the same for the actual non labor units

6. Global changes then required

Subject area - Activity Resource Assignments

Where Resource Type = Material

Then Actual Material units = 0

 

Subject area - Activities

Where activity status is not equal to not started

Then activity status = Not started

 

Subject area - Activities

Where activity status = Not started

Then Remaining duration = Original duration

 

Everything in the project is now not started and reset to original programme

Regards

Roger