Global Change to remove all logic/relationships to external projects?

2 replies [Last post]
V Kutty
User offline. Last seen 5 years 20 weeks ago. Offline
Joined: 17 Jan 2011
Posts: 23
Groups: None

Hi All

 

Just wondering if theres a way of removing all activity relationships to external projects via a global change?

 

Thanks for any pointers

 

V

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

why not go to the scheduling option and turn OFF the link to external projects

Ahmed Aziz
User offline. Last seen 9 years 32 weeks ago. Offline
Joined: 12 Aug 2014
Posts: 25
Groups: None
Hi kutty, I am afraid you cant remove the relations by a global change instead tgere are two other ways: 1. Copy and paste the project and unmark "copy aexternal activity relations" 2. Export to excel (only relationships) open the excel sheet "taskpred". Filter the activities from other project, put a " d" in tge column named "delete this row", import to primavera. Aziz