Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Global Change to remove all logic/relationships to external projects?

1 reply [Last post]
V Kutty
User offline. Last seen 4 years 45 weeks ago. Offline
Joined: 17 Jan 2011
Posts: 23
Groups: None

Hi All

 

Just wondering if theres a way of removing all activity relationships to external projects via a global change?

 

Thanks for any pointers

 

V

Replies

Zoltan Palffy
User offline. Last seen 9 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

go to the schedule options and check ignore relationships to and from otherl projects

also if you export this file to xer then import the file back in durign the importing porcess select modify and under the Data Type: Project section in the Relationships to external Projects you can choose DO NOT IMPORT