I receive a new project schedule bi weekly from our vendor. The previous schedule has the resources, activity codes, and project codes assigned. The new schedule (to be imported does not because the vendor does not use our codes or resources).
There are a couple of ways that I have been updating the schedule:
Straight export/import only udating the dates with "update existing". The problem is so the dates give "wrong" flakey data (dates out in 2020, etc).
Export file to excel and import to new file. The problem with that is the primary resource tab (even though it is in the file) does not check and I can not export the activity or project codes.
Update from import only checking the boxes to update resources, activity codes, and project codes. Can not get the data to change in the new file.
And finally, using Zena but that is not an activity based software.
Any suggestions would be appreciated. Sorry for the long winded explanations, but this is getting frustrating
Thanks