Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Calculation of % Complete at Summary Level

1 reply [Last post]
Ijaz Ahmad
User offline. Last seen 7 years 36 weeks ago. Offline
Joined: 11 Jul 2006
Posts: 42
Groups: None
Hello guys,
Can anybody tell me how P6 calculates the performance % complete at summary Level when we are using it for our Earned Value report.
Thanks
Ijaz

Replies

Rodel Marasigan
User offline. Last seen 17 weeks 5 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Ijaz,
Performance % complete = Activity % complete * BAC. Meaning weighting of each activity base on cost * % complete.