Hi
I have a need to add WBS Summary & LOE activities into a group of contractors' programmes to aide with reporting.
However, in order for these new activities to correctly take on the Start & Finish dates, it appears that I must reschedule the programmes, but this causes the activities within the contractors' programmes to be rescheduled. Therefore the report being created does not show the dates and progress as submitted by the contractors.
Is there a way to calculate the WBS Summary & LOE dates without rescheduling the rest of the programmes?
Or a way to reset the dates and progress back to what they were before rescheduling?
Although I have a good knowledge of planning, this is my first real foray into P6. So nice & clear how to instructions would be most appreciated.
Thanks very much in advance.
Kris
Replies