Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Calculating Duration of Summary Tasks

2 replies [Last post]
Ijaz Ahmad
User offline. Last seen 7 years 45 weeks ago. Offline
Joined: 11 Jul 2006
Posts: 42
Groups: None
Hi guys!
I am finding trouble to customize the duration setting for summary tasks in P5. What I am seeing is that P5 calculates the duration of summary tasks based on calender 5days x 8 hrs/day. How can I change this setting?

Replies

Ijaz Ahmad
User offline. Last seen 7 years 45 weeks ago. Offline
Joined: 11 Jul 2006
Posts: 42
Groups: None
Thanks Andrew
Andrew Podolny
User offline. Last seen 1 year 20 weeks ago. Offline
Joined: 16 Nov 2004
Posts: 130
The duration of summary task are calculated based on Default calendar. To change it go to Enterprise-->Calendars... and
change the Default calendar by checking the box.

Regards,
Andrew