Calculating Duration of Summary Tasks

2 replies [Last post]
Ijaz Ahmad
User offline. Last seen 7 years 26 weeks ago. Offline
Joined: 11 Jul 2006
Posts: 42
Groups: None
Hi guys!
I am finding trouble to customize the duration setting for summary tasks in P5. What I am seeing is that P5 calculates the duration of summary tasks based on calender 5days x 8 hrs/day. How can I change this setting?

Replies

Ijaz Ahmad
User offline. Last seen 7 years 26 weeks ago. Offline
Joined: 11 Jul 2006
Posts: 42
Groups: None
Thanks Andrew
Andrew Podolny
User offline. Last seen 1 year 1 week ago. Offline
Joined: 16 Nov 2004
Posts: 130
The duration of summary task are calculated based on Default calendar. To change it go to Enterprise-->Calendars... and
change the Default calendar by checking the box.

Regards,
Andrew