Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to show Suspended activity more than one time

3 replies [Last post]
Haresh Jayanth
User offline. Last seen 6 years 39 weeks ago. Offline
Joined: 24 Aug 2006
Posts: 219
Suppose , if the activity is suspended more than once , how i can reflect the same using suspend activity option. In p3.1 , we can show only one time , how about in P6, is there any solution for the same.....

Replies

Rafael Davila
User offline. Last seen 1 week 4 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241
Haresh,

Our experience with P3 was that it was very bad at tracking period performance, hard or even impossible to edit, even the trick of using negative entries to the last period was too crude. Better start considering other software more up to date where you can edit multiple individual actuals to the minute and to the cent or equivalent fraction of an Euro. You can say anything about the future but lying about the past will come to the surface at the blink of an eye in a court claim.

For future suspension(s), when known it will happen, the correct way is to model this by splitting the activity into various separate activities and allow CPM logic and resource leveling algorithms drive them as CPM is not always driven only by calendars, very frequently by limitations on resource availability, let CPM show all related metrics for each split. Remember that each split shall have its own resource allocation, its own float, its own duration, ES, EF, LS, LF, costs and so on, take time to explain the other side schedules are dynamic and continuously must be adjusted, if there is need for a split then let it be. Suspension functionality is intended for when it is/was unforeseen, if expected because of changed conditions or even because of a change in plans then the correct way is to split the activity. Rashid got it right.

Best regards,
Rafael
Rashid Iqbal
User offline. Last seen 2 years 17 weeks ago. Offline
Joined: 7 Apr 2010
Posts: 70
Why not cut the activity ????

R
Rodel Marasigan
User offline. Last seen 2 days 9 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Haresh,
Suspend and Resume in P3.1 and P6 are the same. You can only suspend an activity already started and enter the estimated resume date. After resume date become actual you can suspend again the activity. If multiple suspended plans are require then you need to define a calendar with non working period as suspended period.