Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to Make PDF from more than one layouts in one go

No replies
Mohammad Rahmani
User offline. Last seen 1 year 48 weeks ago. Offline
Joined: 18 Jan 2016
Posts: 3
Groups: None

Hi All

Good morning, 

 

I have below question and I appreciate if you give me any soultion,

 

I have 8 projects and more than 40 contractors and one layout for each, every week I create 40 layouts and 40 repetitive works, is there any way to create PDfs from layouts in one click?

 

I also tried reports but as I have more than one projects open it dosen't save my repoort, and I think it is a bug from Oracle.

 

I look forward for any suggestion and thanks from now.

Stay safe

Mohammad

Zoltan Palffy
User offline. Last seen 1 week 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

in P6 go to tools then reports then batch reports and batch them