Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to Auto-calculate Duration form Activity with more than 1 resources loaded

1 reply [Last post]
Mahisha M. Reno
User offline. Last seen 8 years 1 week ago. Offline
Joined: 28 May 2015
Posts: 3
Groups: None

Howdy,

Good day everone, currently i am developing a P6 schedule with auto-calculated duration based on the budgeted qty loaded to certain activities. the activities duration type is fixed unit / time

There are some activities assigned with 2 resources, and both resources are driving the duration of the activity. (previously i dont have a problem with the activity which assigned with only 1 resource)

the idea is like this, I expect P6 could calculate the duration of the activities based on only 1 resource which assigned to the activities, and the other resource load will be spreaded based on the duration calculated from the budget unit of the 1st resource.

for example, on the highlighted activities on teh picture bellow, "spool installation" has Dia-Inch qty & spool EA qty budget to complete (i use this as the remaining quantities for the works that need to be completed)

2478
capture1.jpg

When the budget unit asigned, Dia-Ins = 12831 Dia (with budgeted unit/time : 273/d) and Spools - EA = 1128 (without define spesific unit/time, so P6 gave the default number), the activity's duration calculated based on both remaining budget qty and budgeted unit/time.

What i hope is, the duration is calculated only from the budgeted Dia-Ins, and the spools - EA production's qty spread will follow the duration. If we go to the resource assignment spread bellow,

2479
capture2.jpg

The dia-inc are completed on 5 Jun 15, and the spool goes to 25 Jul 15.

 

My question is, can we use the driver of the duration of fixed unit/time activities with only from "dia-Inch" resources? instead of claculate both resources which assigned to the activities?

Cheers,

MRE

Replies

Zoltan Palffy
User offline. Last seen 22 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

make sure that the activity type is resource dependent this will use the resource with the largest mamhours or units to determine the duration.