Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

scheduled % complete vs actual % complete

4 replies [Last post]
kumar s
User offline. Last seen 8 years 29 weeks ago. Offline
Joined: 26 Jan 2010
Posts: 159
Dear All,

please guide me


In the activity report layout i am comparing the schedule % complete with the actual % complete.

for the schedule % complete in the summary bar it is showing as 0 % complete even if the activites are 100% complete.
why is this happening ...

here is the link to the snap shot of my layout ...
http://img687.imageshack.us/img687/5333/newbitmapimage3g.png


please help me guys...

Replies

Rodel Marasigan
User offline. Last seen 7 weeks 4 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Satishan,
If you looked at the previous project, you find it is cost loaded. It may using only dummy cost to weight the activities. Below is link for some example on how to cost load you activities.

Weight Post#2
kumar s
User offline. Last seen 8 years 29 weeks ago. Offline
Joined: 26 Jan 2010
Posts: 159
Dear Rodel,

you are correct that the project is not cost loaded.
but how can we get the schedule % complete without the cost load.for the previous project the % is showing correctly in the summary bar.
for this project only there is a problem.
is there any ting to do for the resource allocation or some settings has changed...


Satishan....
Rodel Marasigan
User offline. Last seen 7 weeks 4 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
satishan,
The reason is because you program is not cost loaded. P6 calculates % Complete using budget cost.
Ali Farhat
User offline. Last seen 14 years 2 weeks ago. Offline
Joined: 23 Oct 2008
Posts: 120
Groups: None
I dont have a good explanation, but you’ld better check the technique for computing performance % complete @ WBS window for your baseline schedule. I think the problem is there..if there is a problem