How to Export Actual % Complete Vs. Planned % in Excel

3 replies [Last post]
Cecil Soliva
User offline. Last seen 6 years 44 weeks ago. Offline
Joined: 17 Apr 2004
Posts: 20
Good Day Planners,

Any planners could help me exporting Actual % Complete Vs Planned % in Spread sheet (Excel)showing time period, say by weekly or monthly? or is this possible in P6?

Thank you,

Cecil

Replies

Arnold Puy
User offline. Last seen 9 years 24 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Cecil,

You are Welcome.



Cecil Soliva
User offline. Last seen 6 years 44 weeks ago. Offline
Joined: 17 Apr 2004
Posts: 20

Thanks Arnold...


cecil
Arnold Puy
User offline. Last seen 9 years 24 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Cecil,

You can use "Reports" Directory or "Assignment". But you need to convert this data into percent in Excel by dividing them into 100.

Go to Project --> Resource Assignments.

Regards,

Arnold