Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to Export Actual % Complete Vs. Planned % in Excel

3 replies [Last post]
Cecil Soliva
User offline. Last seen 7 years 15 weeks ago. Offline
Joined: 17 Apr 2004
Posts: 20
Good Day Planners,

Any planners could help me exporting Actual % Complete Vs Planned % in Spread sheet (Excel)showing time period, say by weekly or monthly? or is this possible in P6?

Thank you,

Cecil

Replies

Arnold Puy
User offline. Last seen 9 years 47 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Cecil,

You are Welcome.



Cecil Soliva
User offline. Last seen 7 years 15 weeks ago. Offline
Joined: 17 Apr 2004
Posts: 20

Thanks Arnold...


cecil
Arnold Puy
User offline. Last seen 9 years 47 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Cecil,

You can use "Reports" Directory or "Assignment". But you need to convert this data into percent in Excel by dividing them into 100.

Go to Project --> Resource Assignments.

Regards,

Arnold