resource reports- hourly distribution
Forum Sponsor
Top Posters
James Williams
74 posts
Abkar Bannayan
25 posts
christiandt
0 posts
J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
GeoVe
0 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Arnold,

You don’t need to change the duration format, and it will work as long as the resource analysis is in hour.
Alaa,
How many hours per day are they working? Are you using shift/day?
You can organize your resource by WBS level 4 then Resource then Start. Under Start group interval change to day as shown below
Hi Alaa,
Go to Resource Assignment and Group it by Resource ID or Name.
Regards,
Arnold
thanks arnold
actually here I have 2 problems
1- I want to see all resources fro each unit separately
2- the resource distribution in hour
I will try what you advice and get back to you
Hi Alaa,
Is your Original Duration is in Hour? Otherwise, if not the resource distribution will be in days.
Change the Day into Hour. Go to Edit --> User Preferences --> Time Units Tab, "Units & Durations Format". Similarly, change the Resource Analysis from Day to Hour.
When done, try to adjust the Timescale, Date Interval to "Day/Hour".
Regards,
Arnold