Invalid Relationship

5 replies [Last post]
moutaz aldeib
User offline. Last seen 2 years 43 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None
Dear Planners,

In the schedule report there is in Error "Milestone Activities with invalid relationship"

What that means "invalid relationship"?

Regards,

Moutaz

Replies

Joel Villanueva
User offline. Last seen 12 years 23 weeks ago. Offline
Joined: 7 Mar 2010
Posts: 21
Dear Moutaz,

"Invalid Milestone relationship" happens when you change the Activity type (i.e. from Finish milestone to Start milestone or vice versa) and relationship type is already assigned prior the change.

Note:

1.)For Start Milestone relationship should be SS&FS for predecessor and SS,FS&SF for successor.
2.)For Finish Milestone relationship should be FF,FS&SF for predecessor and FF&FS for successor.

Regards,
Joel
Abed Prnd
User offline. Last seen 13 years 42 weeks ago. Offline
Joined: 26 Feb 2009
Posts: 37
Dear Moutaz

maybe there is a loop (cycle) in project network. consider 4 activities with following relations:
-------------------------
predecessor----->activity
-------------------------
e--------------->b
b--------------->c
c--------------->d
d-------------->e

if so,it’s likey to get an error message. i don’t know if PM alows entering such relations or not, but "check integrity" and make sure there’s no cycle.

Regard,
Abed
Rodel Marasigan
User offline. Last seen 11 weeks 3 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Moustaz,
The best way to trace the error is by running Check Project Integrity.

Select Tools-> Check Project Integrity
Tick Automatically fix correctable errors and tick Log to file
Click … buttons and enter destination directory and filename (default: CHKDATA.TXT)
Click Check and when finished click View Log. It will show all the error found on your schedule and you can easily trace & fix the cause.
moutaz aldeib
User offline. Last seen 2 years 43 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None
Dear Rodel,

It is not imported from other software, but the open end activities are too much.

Regards,

Moutaz
Rodel Marasigan
User offline. Last seen 11 weeks 3 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Moutaz,
Is this schedule import from other software (i.e. MS Project)? Check the predecessor and successor, it maybe link to WBS summary activity.