Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

% completes becomes Zero

4 replies [Last post]
Salman Ahmed
User offline. Last seen 14 years 25 weeks ago. Offline
Joined: 2 Mar 2010
Posts: 54
Hi all,

Please let me know what is the reason that when I input some % completion (say 20%) and schedule the project, This % completion becomes Zero.

Thanks in advance.

Replies

Arnold Puy
User offline. Last seen 9 years 43 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Salman,

I guess you changed your remaining duration or perhaps the finish date.

This will happen if your remaining duration is greater than original duration. Try to check this and let us know.

Regards,

Arnold
Salman Ahmed
User offline. Last seen 14 years 25 weeks ago. Offline
Joined: 2 Mar 2010
Posts: 54
I have done the following:

check marked the actual start, assigned the %, updated the actual units, then F9. The result after schedule goes back to zero%, actual units too becomes zero.