Hi,
As far as i know, P6 does not support subprojects like P3. the question starts here.
I have to change values of resources in a massive schedule which is consisted of 14.000 activities and 55.000 resource assignments.
I can export these assignments & resources into excel. but after re-assigning the values for resources and stepping up to import process, p6 gives an error, written: `your system is out memory.’ and can not complete the import process. I divided the import files into 500 resource assigment each. But p6 gives the same error. so it became obvious that the problem is in the massive size of the schedule in p6, this has to be divided.
Sectional Schedule is consisted of two subsection (in different WBS) and if i can divide these two subsection (using their WBS) into two different project, (approximately 7000 activities in each) import process can be completed i suppose.
Note: these two subsection is linked to each other with many activities, and i don’t want to lose any link.
Do you have any advise or method that can be used for creating a subproject or anything else that can divide my schedule into two reasonable schedules?
Your help is appreciated.
Regards
Replies