pct complete & RD unlink

4 replies [Last post]
michael ramos
User offline. Last seen 7 years 24 weeks ago. Offline
Joined: 10 Feb 2009
Posts: 25
Groups: None
hi planners

how can i unlink % complete and remaining duration in p6, i will use it for just a few activities?



thanks

Replies

Ali Farhat
User offline. Last seen 14 years 6 weeks ago. Offline
Joined: 23 Oct 2008
Posts: 120
Groups: None
I go for what Arnold said...
Arnold Puy
User offline. Last seen 9 years 28 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Michael,

Try to use Physical % Complete. It is mnually user’s input.

Regards.
michael ramos
User offline. Last seen 7 years 24 weeks ago. Offline
Joined: 10 Feb 2009
Posts: 25
Groups: None
hi arnold,

when i am changing duration % complete, remaining duration still changes.

i already untick the option you posted below.

my question is to unlink the duration % complete and RD.

thanx again

Arnold Puy
User offline. Last seen 9 years 28 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Michael,

Go to Project Detail --> Calculations Tab --> Under Resource Assignments, untick the "Recalculate Actual Units and Cost when duration % complete changes".

Regards,

Arnold