% completion link/unlink RD and Actuals

4 replies [Last post]
Rashid Iqbal
User offline. Last seen 17 years 15 weeks ago. Offline
Joined: 3 May 2005
Posts: 94
Groups: None
Hi,

I want to arrange the ’settings’ so that when activties are updated for % completion, the actuals for the resources and the RD is automatically calculated. And is it possible that for some activties in the same schedule I could unlink the % completion from the resources actual and RD.

Any help would be highly appreciated

Regards
Rashid

Replies

Rashid Iqbal
User offline. Last seen 17 years 15 weeks ago. Offline
Joined: 3 May 2005
Posts: 94
Groups: None
Thanks Bill, I’ll try your suggestions.

Regards
Rashid
Bill McMichael
User offline. Last seen 12 years 27 weeks ago. Offline
Joined: 12 Dec 2004
Posts: 73
Groups: None
To recalculate actual units and costs when % compl changes, there is a project level option to set this. Go to the project’s screen, select your project, and choose calculations tab on the bottom form.

There is also a % compl type setting for each activity. For activities where you want the percent complete to be independent of durations, units, and costs, choose "physical". This can be set either in columns or on the activity form -- general tab. When you show Activity % as a column, it will display the appropriate percent complete.

Regards,
Bill
Rashid Iqbal
User offline. Last seen 17 years 15 weeks ago. Offline
Joined: 3 May 2005
Posts: 94
Groups: None
Thanks for answering though i am trying to figure out the same in P3e/c.

Regards
Rashid Iqbal
Raja Izat Raja Ib...
User offline. Last seen 13 years 8 weeks ago. Offline
Joined: 2 Jun 2005
Posts: 299
Hi ,
U just go to tools > option > autocost rules and unlink RD.
regards