import pct to p6

2 replies [Last post]
Johnny Wee
User offline. Last seen 6 years 50 weeks ago. Offline
Joined: 23 Jul 2007
Posts: 21
Groups: GPC Qatar
hi all

i am trying to learn importing excel file to p6

i notice that i cannot import duration percent complete without modifying its remaining duration also, what is the best way to update using excel? or maybe i’m missing one important point.

hope somebody can help.

thanx

Replies

Johnny Wee
User offline. Last seen 6 years 50 weeks ago. Offline
Joined: 23 Jul 2007
Posts: 21
Groups: GPC Qatar
thanx
Arnold Puy
User offline. Last seen 9 years 28 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Johnny,

You cannot modify, change and edit in Excel all columns title having the symbol of (*). If you want to change your duration % complete, you need to change your remaining duration and put the actual start.

The only workaround is to create a UDF and export to excel then create global change.

HTH.

Regards,

Arnold